Conformed drawings vs record drawings vs as-builts

Definition

Conformed, record and as-built drawings: Three sets from the two ends of a project. Conformed drawings are the bid set with the addenda incorporated, made at award. As-built drawings are the contractor’s marked-up set recording what was actually built. Record drawings are the architect’s drawings revised to reflect those markups after completion, prepared as an additional service when the owner asks.

Conor McMichael · Architect. Founder, LODE

Last updated

An owner’s facilities manager once asked me, two years after a project closed, for the as-builts. I sent the record drawings. She sent them back: these are your drawings, she said, I want the contractor’s. She was right, and the distinction she was drawing is one most architects blur in conversation and should never blur in a contract. The set the contractor marked up in the trailer and the set I redrew from it are different documents, made by different parties, and they certify different things.

The conformed set belongs in the same conversation because it is the other end of the same thread. The conformed set is where construction started; the record set is where it finished; everything between them is the revision history. A firm that keeps all three, and keeps them distinct, can answer any question about a building that a later owner, tenant or lawyer will ask.

Three sets, two ends of the project

The names are close and the documents are not, so the table does the work. The column that matters most is the last one: what each set certifies. The conformed set certifies nothing about the building; it records what was agreed. The as-built markups are the contractor’s statement of what was done. The record drawings are the architect’s redrawing of that statement, and they say so on their face.

SetWho prepares itWhenWhat it certifiesContract basis
Conformed drawingsArchitectAt contract awardNothing about the building. It records the documents as agreed, with the addenda incorporatedThe bidding documents and addenda under A701-2018; the architect’s bidding-phase services under B101-2017
As-built drawingsContractor, in the fieldKept current through construction; delivered at completionThe contractor’s record of field changes, selections and deviations from the documentsA201-2017 §3.11: one set at the site, marked currently, delivered to the architect at completion
Record drawingsArchitect, from the contractor’s markupsAfter substantial completionThat the drawings have been revised to reflect information furnished by the contractor; not the accuracy of that informationB101-2017 §4.1.1.15 and §4.1.1.16: as-designed and as-constructed record drawings, both supplemental services the owner must select
The references are to the current AIA documents; the documents are the authority and this page paraphrases them.

Why the architect’s set is not called as-built

The phrase as-built drawings makes a claim: this is how the building was built. An architect cannot make that claim honestly, because the architect was not there for most of it. Site visits under a standard agreement are periodic, and the architect’s observations are of the work in progress at intervals, not of every pipe before it was covered. What the architect can honestly say is that the drawings have been revised to incorporate the changes the contractor reported. That is a record drawing, and the AIA documents use that term for the architect’s set deliberately.

The distinction is not pedantry. A record drawing that is labelled as-built, and that turns out to be wrong because the contractor’s markup was wrong, has put the architect’s name on the contractor’s error. Record drawings carry a note to the effect that they are based on information furnished by the contractor and that the architect has not verified it. The note is standard, it is honest, and it is the first thing a lawyer looks for.

What the contractor’s markups must contain

A201-2017 §3.11, Documents and Samples at the Site, is short and specific; in paraphrase, the contractor maintains at the site one copy of the drawings, specifications, addenda, change orders and other modifications, in good order and marked currently to indicate field changes and selections made during construction, together with the approved submittals, and delivers them to the architect when the work is complete. Marked currently is the phrase to hold the contractor to: an as-built set drawn from memory in the last week of the job is not what the clause describes.

In practice the markups that matter are the ones nobody can see afterwards. Where the underground utilities actually run. Where the plumbing was rerouted around a beam. Which of two alternate details was built at each location. Dimensions that moved. Equipment that was substituted, and the approved submittal that substituted it. A good superintendent keeps a set on the trailer wall and marks it in red as the work goes in; a good architect asks to see it at every site visit, because the request is what keeps it current.

  • Field changes: anything built differently from the current drawings, with the RFI, ASI or change order that allowed it.
  • Concealed conditions: routing and locations of work that is covered by the time anyone else looks.
  • Selections: the alternate, the colour, the product chosen where the documents allowed a choice.
  • Dimensions: the ones that moved, measured, not estimated.
  • Approved submittals: filed with the set, because they are the record of what was actually supplied.

What the architect’s record set contains

The record drawings start from the current set, which is the conformed set with every later revision incorporated, and add the contractor’s markups. The order matters. An architect who starts from the bid set and tries to add everything at once is redoing the revision history from scratch. An architect who has kept the set current through construction, superseding sheets as each ASI and bulletin landed, has a record set that is one pass of markups away from done.

Each record sheet carries three things: the revision history that got the sheet to its final state, the as-built information drawn in and attributed, and the record-drawing note. The sheet index is reissued as a record index, listing every sheet with the revision it ended on and the issuance that put it there. That index is the single most useful page in the set for whoever inherits the building, because it is the one page that says how many times each drawing changed and why.

B101-2017 distinguishes two services here, and the distinction is worth putting in the proposal. As-designed record drawings, §4.1.1.16, are the architect’s drawings updated to reflect the changes the architect made during construction: the addenda, ASIs, bulletins and change orders. As-constructed record drawings, §4.1.1.17, go further and incorporate the contractor’s field markups. The first can be produced from the architect’s own records; the second depends on the contractor having kept theirs.

Sheet indexconformed · 5 of 38 sheets
SheetTitleRevIssued in
Architectural
A
A101Floor Plan — Level 12Addendum 2
A102Floor Plan — Level 20Bid Set
A201Enlarged Plan — North Stair4Bulletin 1
A301Building Section3ASI 03
A501Stair Details4Bulletin 1
A record index: every sheet, the revision it ended on and the issuance that put it there.

Conformed vs record: the same set, years apart

Put the conformed set and the record set side by side and the difference between them is the history of the project. Every sheet that changed, changed because of an instrument: an ASI, a bulletin, a construction change directive, a change order, a field condition. If every one of those instruments superseded its sheets properly, with the old sheet kept and the new one marked, then the record set is simply the last page of a history that began with the conformed set, and the two together are a complete account.

If they did not, the record set is a reconstruction. Someone sits down at closeout with the conformed set, a folder of PDFs named by date, and the contractor’s markups, and tries to work out which sheet is the latest. This is where record drawings go wrong, and it is why the discipline that produces a good record set is not applied at closeout but during construction, one issuance at a time. The conformed set page explains how the baseline is made; this is why it matters that the baseline is never overwritten.

Field set vs record set

Two more names belong in this conversation because they are the ones a crew and an owner actually use. The field set is the current set: the drawings the contractor should be building from today, which is the conformed set with every revision to date superseding its sheets. The record set is what was built. During construction they are different documents and both are needed; at substantial completion the field set stops changing and becomes the basis of the record set.

LODE keeps both, under those names. The Field Set is regenerated on every issuance and holds only the current sheets and sections. The Revision Record Set holds every superseded sheet, stamped, so the history is kept rather than overwritten. On the last day of construction the Field Set is the as-designed record, the Revision Record Set is how it got there, and the contractor’s markups are what turn it into the as-constructed record. The Field Set and the Revision Record Set in Files.

When each set is due

The conformed set is due at award, before the first construction meeting. The contractor’s as-built markups are due when the work is complete, under §3.11, and in practice should be reviewed at substantial completion and listed among the closeout submittals so that final payment is not processed without them. The record drawings, if the owner has commissioned them, follow after the markups arrive; a reasonable proposal gives a number of weeks from receipt of complete markups, because the architect cannot start without them and should not be held to a date the contractor controls.

The failure that produces most arguments is the unspecified one: an owner who assumed record drawings were part of the fee, an architect who assumed they were not, and a contractor whose markups were never requested. The fix is three lines, one in each agreement: who marks up, who redraws, and who pays for the redrawing.

Frequently asked questions

What is the difference between record drawings and as-built drawings?

As-built drawings are the contractor’s marked-up set, kept at the site during construction and delivered at completion under A201-2017 §3.11. Record drawings are the architect’s drawings revised to incorporate those markups, prepared after completion as an additional service under B101-2017. The architect’s set is called record, not as-built, because the architect did not observe every condition it shows.

Who prepares record drawings?

The architect, and the consulting engineers for their disciplines, from information furnished by the contractor. The contractor prepares the as-built markups the record drawings are based on. Record drawings normally carry a note that they rely on the contractor’s information and that the architect has not verified it.

Are record drawings part of the architect’s basic services?

Not under the standard AIA agreement. B101-2017 lists as-designed record drawings (§4.1.1.16) and as-constructed record drawings (§4.1.1.17) as additional services, to be included and paid for only if the owner selects them. Many owners assume otherwise, which is why the proposal should say so.

What is the difference between conformed drawings and record drawings?

Timing and content. Conformed drawings are made at contract award and incorporate the addenda issued during bidding; they are the baseline construction starts from. Record drawings are made after completion and incorporate every change made during construction plus the contractor’s field markups; they are where construction ended.

What is the difference between the field set and the record set?

The field set is the current set, what the contractor builds from today: the conformed set with every revision to date. The record set is what was built, assembled after completion from the contractor’s markups. LODE keeps the Field Set and the Revision Record Set side by side through construction, so the record set starts from a complete history.

Does the architect certify that record drawings are accurate?

No. Record drawings reflect information furnished by the contractor, and the AIA’s instructions for B101-2017 say the architect is not responsible for the accuracy or completeness of the as-constructed record drawings. The architect records that the drawings were revised to incorporate that information, not that the information is correct.

In LODE

The record set is the history, kept.

LODE keeps every issuance from the bid set onward, so the Field Set at substantial completion is the conformed set with every ASI, bulletin and change order superseding its sheets in order, and the Revision Record Set holds every superseded sheet, stamped. The record index is the Field Set’s sheet index on the day the work finished. How closeout works in LODE.

Closeout deliverables, the contractor’s markups among them, are tracked in the same project as the submittals that produced them, so the record drawings start from a complete set of inputs rather than a request for them.

Deliverables Registerseeded from approved submittals
O&M Manual — HVACSub 032Received
Warranty — RoofingSub 027Outstanding
Door Hardware keying chartSub 019In review
Closeout starts itself mid-construction — every approved submittal knows what it owes the record

Close out from the set you built from.